Description of Project

Northern Group has been involved in numerous BER projects. St Clares Catholic Primary School is another prime example.

The project involved the demolition and clearing of existing dilapidated car park surface and lawn area to make way for a new 750m2 at grade bitumen car park, inclusive of kerb and guttering, concrete layback and kerb only work. In addition minor upgrade was undertaken to the existing stormwater infrastructure servicing the area.

Northern Group managed the entire works from set out, through base placement, compaction and lying of the finished surfacing using synergy equipment and synergy qualified sub contractors.

Furthermore 300m2 of car park surface was too restored by profiling existing surface and laying new asphaltic concrete 30mm thick.

In conjunction with the above Northern Group undertook the bulk and detailed excavation for the new multipurpose building and upgrade to the existing canteen area within the school grounds.

Northern Group undertook the project within the constraints of limited school working hours and with consideration of the sensitive environment in and around operating school grounds.